home
***
CD-ROM
|
disk
|
FTP
|
other
***
search
/
Apple Reference & Presen…rary 6 (Reseller Edition)
/
Apple Ref. & Pres. Lib.v6.0.toast
/
pc
/
5-Fonts & Software
/
Applications
/
MacProject II
/
MacProject II Help
/
card_117215.txt
< prev
next >
Wrap
Text File
|
1989-09-27
|
2KB
|
119 lines
-- card: 117215 from stack: in
-- bmap block id: 0
-- flags: 0000
-- background id: 64774
-- name: Assigning Resources 3
-- part 1 (field)
-- low flags: 01
-- high flags: 0000
-- rect: left=11 top=57 right=72 bottom=233
-- title width / last selected line: 0
-- icon id / first selected line: 0 / 0
-- text alignment: 0
-- font id: 3
-- text size: 10
-- style flags: 256
-- line height: 13
-- part name: subhead
-- part 2 (field)
-- low flags: 01
-- high flags: 0002
-- rect: left=409 top=260 right=275 bottom=464
-- title width / last selected line: 0
-- icon id / first selected line: 0 / 0
-- text alignment: 1
-- font id: 3
-- text size: 10
-- style flags: 0
-- line height: 13
-- part name: pagexofy
-- part 3 (button)
-- low flags: 00
-- high flags: A003
-- rect: left=30 top=108 right=128 bottom=216
-- title width / last selected line: 0
-- icon id / first selected line: 0 / 0
-- text alignment: 1
-- font id: 3
-- text size: 10
-- style flags: 0
-- line height: 13
-- part name: Task Info Window
----- HyperTalk script -----
on mouseUp
go card id 114649
end mouseUp
-- part contents for background part 31
----- text -----
Setting Up a Project
-- part contents for background part 32
----- text -----
Assigning Resources
-- part contents for card part 1
----- text -----
To allocate a resource to a task:
-- part contents for background part 6
----- text -----
Select a task and choose Show Task Info from the Task menu.
Under Resource, type the name of the primary resource for the task, or use Resource List from the Resource menu to import the name of the a resource.
Under Work-Days, type the total number of work days (or other units of duration) the resource will need to work on the task.
-- part contents for background part 27
----- text -----
1.
2.
3.
-- part contents for background part 7
----- text -----
Under Number, type the number of people or pieces of equipment for this resource.
Under %Effort, type a number for the percentage of the resource’s available time that will be spent on this task.
If you want to allocate resources to more than one task, press Return to put the changes into effect and move on to the next task.
Close the Task Info window.